Andrew Hall, president and CEO of Yukon Energy, answers a question regarding new energy projects in the Yukon during a press conference in Whitehorse on Sept. 5. (Crystal Schick/Yukon News)

Yukon gets cash for upgraded transmission line, energy storage system

Both projects are aimed at delivering more reliable energy to Yukoners

Roughly $60 million has been earmarked for two energy projects: an energy storage system and replacement of a portion of the Keno-Stewart transmission line.

Ottawa is providing more than $39.2 million in total, with up to $16.5 million going to the battery project, which is to store excess hydro power during off-peak hours while reducing the reliance on diesel fuel.

“These two projects are critical to Yukon Energy’s ability to build a sustainable, reliable and affordable electricity system that Yukoners need today and the robust energy system that the territory needs to continue its growth in the future,” said Andrew Hall, president and CEO of Yukon Energy at the announcement Sept. 5.

Thirty-one kilometres of the transmission line is being eyed for replacement, between Mayo and McQuesten. It’s being called the “first phase” of work with more to likely follow eventually, Hall said.

The federal government is providing more than $22.7 million to the project; Yukon Energy is contributing $7.8 million; the Yukon government is providing $3.4 million.

The new line will have a higher capacity, Hall said – voltage will be doubled.

“This line is more than 65 years old and has reached end of life,” he said. “We’ve had consultants tell us it’s the worst line they’ve ever seen.”

The project is shovel ready, he said, having been signed off by the Yukon Environmental and Socio-economic Assessment Board.

It will be completed in 2020.

Hall said Victoria Gold’s Eagle mine, which is slated to start pouring gold on Sept. 17, will benefit from the project, along with Keno and Mayo residents.

John McConnell, CEO of Victoria Gold, said, “The current line meets our needs, quite comfortably.”

Asked how the new line will help operations then, he said, “It’s not, really. It’s just that that line is worn out and if it fell down tomorrow, we’d have a problem, but increasing the capacity is not for Victoria (Gold), it’s for other industrial developments in the future.”

The new transmission line raises a lot of questions, said Scott Kent, the Yukon Party’s energy critic.

He said it’s a positive for the territory (the Yukon Party pushed for the same thing when it was in power.) But there are issues that need to be clarified, namely whether taxpayers will see their power bills increase now that Yukon Energy is covering a fair amount of the cost and, if so, by how much.

“Is there a utility board hearing that’s required? We need some more clarity from the Liberals on those outstanding questions,” he said.

Yukon Energy’s communications manager said it’s unclear what the impact to ratepayers would be at this time.

“Like all investments we make in Yukon’s electricity system,” said Stephanie Cunha, “we will make an application to the Yukon Utilities Board to include these costs in customer rates when the projects are complete. The YUB (Yukon Utilities Board) will review those costs at that time.

“One thing to note is that as the major user of the new Mayo to McQuesten line, Victoria Gold will pay for the majority of our $7.8 million investment in that line. Right now, according to our Purchase Power Agreement with Victoria Gold, the mine will pay 85 per cent of the fixed costs of the line through a fixed charge.”

The eight-megawatt battery storage unit will be capable of reducing 20,000 tonnes of greenhouse gas emissions, Bagnell said.

Hall said it will be the largest device of its ilk in the North, maybe the largest in the country.

“It will serve as flexible and dependable supply of electricity for all Yukoners connected to the grid when demands are high or during emergency,” he said. “It will also help us to prevent outages from happening or responding to outages once they occur.”

Yukon Energy is contributing $8.5 million towards the project.

It will go in the Whitehorse area, though no specific location has been settled on yet.

Contact Julien Gignac at julien.gignac@yukon-news.com

Get local stories you won't find anywhere else right to your inbox.
Sign up here

Just Posted

From Whitehorse to the Whitecaps

Joe Hanson is starting his second season with the Vancouver Whitecaps academy

Mount Lorne Mis-Adventure Trail Race doesn’t miss a step

Blue skies and sunshine for a chilly fall race

Canada Summer Games postponed

Yukon Canada Summer Games athletes will now work on mastering skills in preperation for 2022

Site selection for battery project draws ire of nearby landowners

Yukon Energy is accepting public comments on three possible sites for the project

Taking a closer look at the cosmos

Star gazing party scheduled for Sept. 18

Yukon government releases new guidelines for COVID-19 symptoms and sending children to school

The advice sorts symptoms into three categories: red, yellow and green

Nominations closed in Watson Lake byelection

Four candidates are running for mayor

Baggage screening changes begin

Passengers are asked to arrive earlier than normal in order to accommodate the new temporary system

Yukon Government extends education review

The final report is scheduled for release in March 2021

City hall, briefly

A look at decisions made by Whitehorse city council this week

Lawsuit against Freedom Trails settled

The suit was dismissed with consent of all parties

Tank farm takes another step towards development

OCP designation passes second reading

Climate change strategy targets 30 per cent reduction in territory greenhouse gases by 2030

The strategy includes rebates for electric vehicles but puts off mining targets for two years

Most Read