Miles Canyon bridge to reopen this spring

Repairs to the Miles Canyon suspension bridge are ahead of schedule and the popular tourist attraction should be re-opened by the beginning of May, rather than this summer.

Repairs to the Miles Canyon suspension bridge are ahead of schedule and the popular tourist attraction should be re-opened by the beginning of May, rather than this summer.

Temporary repairs are scheduled to begin next week, according to Jennifer Macgillivray with the Department of Community Services.

That will include replacing some of the decaying crossbeams that run across the bottom of the bridge.

More permanent work will take place in the fall, she added, to replace the rest of the aging timbers on the bridge.

“This will allow the bridge to spend more time open and less time under repair,” she said.

Macgillivray said there’s no safety risk to opening the bridge after its temporary repairs are completed next month.

Andco Enterprises Ltd. won the contract for the temporary repairs for about $46,000.

The Yukon government closed the bridge back in October following a safety inspection on Oct. 20.

An engineer with Wood Research and Development Inc., Dan Tingley, carried out a more detailed inspection from Oct. 28-31.

According to Tingley’s final report, the bridge’s towers and suspension cables were in good condition but parts of the main wood structures had deteriorated.

Of the 21 crossbeams on the bridge, 11 have significant decay.

The use of heavy solids in the paint that was applied to the beams has accelerated the decay because it traps moisture inside the wood, preventing evaporation, explained Paul Murchison with the Department of Highways and Public Works at a briefing in December.

The bridge won’t be painted this time, Macgillivray said, and will have the same appearance as when it was originally built.

The stringers, which run underneath the bridge and connect to the deck, are also in various stages of decay.

Pictures in the report showed beams that had partially rotted. Some were cracked and had large pieces that had broken off.

“It is recommended that the bridge remain closed until the above repairs are completed,” Tingley wrote in his report’s conclusion.

“Immediate works to prevent snow build up induced failure or failure under a trespass load might be considered.”

After repairs are completed in the fall, the bridge should have a lifespan of about 50 years, Macgillivray said.

Built in 1922 as a tourist attraction, the 130-foot long bridge was rebuilt in the early 1970s.

Following an inspection in 2008, the towers were rebuilt and new concrete footings were poured, according to the Yukon government.

Work on the bridge was last done in 2010-11, when the timber towers were refurbished and replaced. New concrete footings were also installed under the towers.

Just Posted

Yukon’s Japanese association launches its first sake festival

Former president says the hope is to bring people together to learn

Yukon First Nations, AFN Yukon, CYFN sign climate change emergency declaration

The declaration was signed on the last day of the Yukon First Nations Climate Action Gathering

Yukon Fish and Game Association opposed to moose management proposals

Executive director Eric Schroff said he thinks Yukon government needs to be more transparent

WYATT’S WORLD

Wyatt’s World

Casino taking more time with mine proposal

Statement not expected to be submitted to YESAB until Dec. 31, 2021

Tr’ondëk Hwëch’in to hold general election in April

On top of voting for chief, three councillors, citizens will vote for a deputy chief for first time

Yukon’s minimum wage set to increase by $1 to $13.71 in April

The increase will make the Yukon’s minimum wage the fourth-highest in the country

City news, briefly

Some of the decisions made at the Whitehorse council meeting on Feb 17

Yukonomist: Three questions on Yukon Zinc and China

The case heard recently in Yukon Supreme Court is particularly troubling

Commentary: Highway plans will negatively impact safety

The proposed Alaska Highway work will impact our safety, our communities and our environment.

Olivia Webster is the final musher to finish the Yukon Quest

‘I guess I’ve always been a grandpa’s girl and he’s my best friend, so I kind of wanted to be like him and so I did it’

Yukon’s Rob Cooke and company finish 10th in the 2020 Yukon Quest

Cooke and his 14 Siberians crossed the finish line at 9:07 a.m. on Feb. 15 in Whitehorse

Lights Out Yukon Invitational Basketball Tournament bigger than ever in sixth year

“Honestly, it was the smoothest tournament I think we’ve run yet”

Most Read