Building the Dempster Highway: an engineering challenge

When Yukon Highway No. 5 was built, it penetrated some of the most challenging and enigmatic wilderness in Canada.

When Yukon Highway No. 5 was built, it penetrated some of the most challenging and enigmatic wilderness in Canada. It was the homeland of the Vuntut Gwitchin, the Tr’ondek Hwech’in, and the Nacho Nyak Dun, known only to the families that hunted, trapped and travelled over the land.

The European history for the region consisted of a few noteworthy events. These included the arrival of the Hudson’s Bay Company, the tragedy of the Mounted Police patrol which perished in 1911 and Corporal W.J.D. Dempster, who found their sad remains, and the hunt for the mad trapper of Rat River, which ended on the frozen Eagle River in February of 1932.

Oil exploration commenced on the Eagle Plain around 1954, but the Liberal government of the day refused to consider building a road to this region. The Conservative government of John Diefenbaker was elected in 1957 on an election platform including the “Roads to Resources” program, which was intended to reach and exploit Canada’s vast northern resources.

Under the direction of Alvin Hamilton, the minister of Northern Affairs and National Resources, the Dempster Highway became the centrepiece of this program. With the oil industry proposing to invest $150 million to $250 million in oil exploration, Hamilton stated that $5 million to $8 million would complete the road construction in four or five years. The discovery of oil on the Eagle Plain was announced August 17, 1959.

At first, it was known as the “Flat Creek Road,” the “Flat Creek to Chapman Lake Road,” or the “Flat Creek to Aklavik Road.” Its ultimate destination became the yet-to-be-built community of Inuvik, a former oil well drill site known as Aklavik E-3.

Initial proposals considered three possible routes for the highway, one starting near Elsa and Keno City, the other two originating near Dawson City. Engineers settled upon a route near Dawson that followed the path of Cat trains – Caterpillar tractors pulling strings of sleds – that were hauling equipment and supplies to the drilling rigs on the Eagle Plain.

This route crossed the Klondike River near Flat Creek, proceeded up the north Klondike River valley and followed the Blackstone River as far as Chapman Lake, a distance of 125 kilometres. Survey work progressed through 1958, and construction of the first 48 kilometres began in 1959.

Boyde White, who worked on the construction during the first two years, said the road initially followed the Cat train trails, which ran close to the Klondike River, but after numerous washouts, the road was relocated to higher ground. The first section of the road was built to a lower standard and later required extensive upgrading.

Replacement of Alvin Hamilton by a less enthusiastic Walter Dinsdale as minister, as well as the poor production results of the wells drilled, led to construction being put on hold in 1962. The road was maintained seasonally for the next few years. The only event of note occurred in August 1964, when then minister Arthur Laing, in response to petitions by the Vancouver Yukoners Association and the Yukon Order of Pioneers, directed that the road be henceforth known as the Dempster Highway.

Interest in the highway was rekindled with the announcement of an oil discovery at Prudhoe Bay, Alaska, and the prospect of a pipeline over the Dempster route. From 1970, construction contracts were awarded annually. In 1971, the Department of National Defence built a bridge over the Ogilvie River for $504,000. A second, more challenging bridge spanning the Eagle River was built between July 1976 and July 1977.

Meanwhile, road construction proceeded from both ends until they met between the Eagle River and the Richardson Mountains. The final cost of the 735 kilometre-long highway: an estimated $132 million. An interim ferry was placed on the Peel River in 1979, and on Discovery Day that year, dignitaries including Northern Affairs Minister Jake Epp and member of Parliament Erik Nielsen attended an official ribbon-cutting ceremony near the Klondike River bridge, at the southern end of the highway.

Sadly, John Diefenbaker, the man who conceived of the “Roads to Resources” program in the first place, died two days before the ceremony.

The construction of the highway posed many challenges. It was the most northerly major highway project of its time. It ran through virtually uncharted wilderness and the engineers building the road had little precedent to work with – the only previous construction over similar permafrost terrain was the Alaska Highway. The route was remote, making logistics challenging and construction costly.

The seasonal extremes of weather (that regularly plummeted below the limits of the mercury thermometer in the winter) and daylight (weeks of total darkness in December and January) had to be dealt with. In December 1979, a highway crew became trapped in the Richardson Mountains during a spectacular blizzard and nearly perished before being rescued.

The route had to be selected where rock and gravel were easily reached. Heavy rainfall would cause washouts, which had to be repaired before further work could be done. Sections were moved or grades improved to avoid disastrous repetitions.

Permafrost was a unique challenge during construction of the Dempster Highway. The moisture-laden subsoil, which is rock-hard when frozen, turns to mush when disturbed. Experiments were run to test various methods of insulation to prevent dangerous heat transfers and melting. These were costly and therefore impractical.

Experience determined that a gravel road bed at least 1.4 metres thick, laid on top of the ground without disturbing the subsurface, was sufficient to stabilize the road. Being frozen, the ground is also impermeable. Engineers had to address the resulting problems of water accumulation and drainage.

The Eagle River Bridge was a case study in design for remote permafrost conditions. It was a joint exercise involving engineers from the Department of Public Works, who designed it, the Department of Indian and Northern Affairs, who paid for the materials, and the Canadian army, who built it as part of a 1976-77 training program.

The steel superstructure of the bridge was assembled where it was fabricated in Hamilton, Ontario, to familiarize the engineers with its assembly, and to ensure that every part was accounted for and fit properly. Any problems in these areas would lead to lengthy delays once it was delivered to the site.

Work had to be scheduled around weather conditions. The piles supporting the bridge had to be driven into frozen ground, and then insulated to ensure that the permafrost would not be disrupted.

Because of the sub-zero temperatures at the time that the concrete was poured, the steel components and the surrounding air temperature were kept above freezing to allow the concrete to cure properly. Special polyethylene tents were built over the concrete pile caps and monitored around the clock to ensure that the temperature never dropped during the several days required for curing of the concrete.

Not much thought is given to the challenges that were overcome to construct the Dempster Highway. Every year thousands of travellers drive one of the most spectacular highways in the world without giving a second thought to the road – unless, of course, they have a flat tire.

This article was provided by the Association of Professional Engineers of Yukon.

Get local stories you won't find anywhere else right to your inbox.
Sign up here

Just Posted

Benjamin Poudou, Mount MacIntyre’s ski club manager, poses for a photo in the club’s ski rental area on Nov. 16. The club has sold around 1,850 passes already this year, compared to 1067 passes on Oct. 31 last year. (Crystal Schick/Yukon News)
Early season ski pass sales up as Yukoners prepare for pandemic winter

Season passe sales at Mount McIntyre for cross-country skiing are up by around 60 per cent this year

The City of Whitehorse will be spending $655,000 to upgrade the waste heat recovery system at the Canada Games Centre. (Crystal Schick/Yukon News file)
New waste heat recovery system coming to the CGC

Council approves $655,000 project

Yukon First Nation Education Directorate education advocates and volunteers help to sort and distribute Christmas hamper grocery boxes outside Elijah Smith Elementary School on Feb. 23. (Rebecca Bradford Andrew/Submitted)
First Nation Education Directorate begins Christmas hamper program

Pick-ups for hampers are scheduled at local schools

Cyrine Candido, cashier, right, wipes down the new plexi-glass dividers at Superstore on March 28, before it was commonplace for them to wear masks. The Yukon government is relaunching the Yukon Essential Workers Income Support Program as the second wave of COVID-19 begins to take place in the territory. (Crystal Schick/Yukon News file)
Yukon Essential Workers Income Support Program extended to 32 weeks

More than 100 businesses in the territory applied for the first phase of the program

Cody Pederson of the CA Storm walks around LJ’s Sabres player Clay Plume during the ‘A’ division final of the 2019 Yukon Native Hockey Tournament. The 2021 Yukon Native Hockey Tournament, scheduled for March 25 to 28 in Whitehorse next year, was officially cancelled on Nov. 24 in a press release from organizers. (John Hopkins-Hill/Yukon News file)
2021 Yukon Native Hockey Tournament cancelled

The 2021 Yukon Native Hockey Tournament, scheduled for March 25 to 28… Continue reading

Lev Dolgachov/123rf
The Yukon’s Information and Privacy Commissioner stressed the need to safeguard personal information while shopping this holiday season in a press release on Nov. 24.
Information and Privacy Commissioner issues reminder about shopping

The Yukon’s Information and Privacy Commissioner Diane McLeod-McKay stressed the need to… Continue reading

Keith Lay speaks at a city council meeting on Dec. 4, 2017. Lay provided the lone submission to council on the city’s proposed $33 million capital spending plan for 2021 on Nov. 23, taking issue with a number of projects outlined. (Crystal Schick/Yukon News file)
Resident raises issues with city’s capital budget

Council to vote on budget in December

Beatrice Lorne was always remembered by gold rush veterans as the ‘Klondike Nightingale’. (Yukon Archives/Maggies Museum Collection)
History Hunter: Beatrice Lorne — The ‘Klondike Nightingale’

In June of 1929, 11 years after the end of the First… Continue reading

Samson Hartland is the executive director of the Yukon Chamber of Mines. The Yukon Chamber of Mines elected a new board of directors during its annual general meeting held virtually on Nov. 17. (Joel Krahn/Yukon News file)
Yukon Chamber of Mines elects new board

The Yukon Chamber of Mines elected a new board of directors during… Continue reading

The Yukon Hospital Corporation has released its annual report for 2019-20, and — unsurprisingly — hospital visitations were down. (Crystal Schick/Yukon News file)
Annual report says COVID-19 had a large impact visitation numbers at Whitehorse General

The Yukon Hospital Corporation has released its annual report for 2019-20, and… Continue reading

Whitehorse City Hall. (Joel Krahn/Yukon News file)
City hall, briefly

A look at decisions made by Whitehorse city council this week

Most Read