Clearing work on the Site C dam project near Fort St. John, 2016. Work has gone on for two years, with $1.7 billion spent and more than 2,000 people working. (BC HYDRO)

UPDATE: Weaver’s claims of Site C road damage denied

BC Hydro says sweatlodge, burial ground accommodated

BC Hydro says a road realignment project to make way for the Site C dam on the Peace River would not “pave over” a sweatlodge and disrupt an aboriginal burial site, contrary to claims made by B.C. Green Party leader Andrew Weaver Wednesday.

BC Hydro issued a statement in response to Weaver’s claims, made after a tour of the area this week.

“We are aware of West Moberly and Prophet River First Nation’s concerns about construction activities in the Cache Creek/Bear Flat area in the vicinity of the sweat lodge,” the statement says.

“It is not true that we plan to pave over the sweat lodge. In response to the concerns from the West Moberly and Prophet River First Nations, we have refined the design of Highway 29 to increase the distance between the highway realignment and the sweat lodge. While we acknowledge that the sweat lodge would be in closer proximity to the new road, we determined that we could move the highway an additional eight metres to the north to accommodate planting vegetation or noise abatement measures on the south side.

“These measures would act as a buffer between the sweat lodge and the highway. The total distance from the centre line of the highway to the sweat lodge is now 45 metres. In addition, we are willing to discuss other mitigation measures in relation to the sweat lodge, including constructing a new spiritual centre or other additional cultural facilities elsewhere in the Cache Creek/Bear Flat area.

“Following extensive archeological work, BC Hydro has not confirmed any Aboriginal burial sites in the project area; however, we continue to listen and investigate specific sites as advised by First Nations communities.

“In March, the West Moberly and Prophet River First Nations notified BC Hydro of the location of a potential burial site. We have refined the design of Highway 29 to lengthen the bridge by 50 metres to avoid ground disturbance of this site, and raised the height of the bridge to provide about two metres clearance above the specific site to avoid disturbing the site.

“We are meeting with them this week to further discuss their concerns.”

Weaver spoke to reporters in Victoria after touring the area with the project’s most vocal opponents, leaders of the West Moberly and Prophet River First Nations and Ken and Arlene Boon, the farmers who have refused to move from the area affected by the construction and eventual flooding near Fort St. John.

“What’s remarkable about all of this is that there are a number of options for the road,” Weaver said. “They could continue building the road, but the road does not have to be the option that goes through the sweatlodge, through the Boons’ house and through another house down the road and across a burial site.”

The location of the sweatlodge is “new information,” Weaver said. He was not able to say how long it has been there.

Weaver reiterated the reasons why he wants the Site C project stopped, two years into construction with $1.7 billion spent and more committed to major earthworks and powerhouse contracts. He said he supported the original proposal in 2009 when the estimated cost was less than $6 billion, but now the cost is estimated at nearly $9 billion and he expects it to go higher.

Based on the higher cost, BC Hydro would lose money on power supply agreements with major liquefied natural gas producers that have yet to commit to construction, he said.

Premier Christy Clark made her own trip to Fort St. John this week, to meet with local B.C. Liberal MLAs and tout the employment benefits of the project. More than 2,200 people are working on the site, with a construction timeline leading to the dam coming online in 2024.

more to come…

Just Posted

Restored totem pole, a gift from B.C., unveiled in Whitehorse

The Gawagani Pts’aan, meaning “Peace Totem Pole,” was gifted to the Yukon government in 1971.

UPDATED: YG is ‘failing’ First Nations students, says chair of the Chiefs Committee on Education

Bob Dickson said the Yukon government’s unilateral approach to education ‘doesn’t fly’ anymore

Yukon River Quest team paddling to honour Indigenous women, girls

Team Dinjii Ni’jootl’i Ka’t is trying to send a positive message as well as raise awareness about MMIWG

Whitehorse council defers vote on climate change declaration until September

The decision comes after a lengthy debate in front of a packed room

Yukon College taking applications for new Yukon First Nations art program

Yukon College has opened the application process for its new Yukon First… Continue reading

Athletes take on rain for Grey Mountain Summer Solstice Fun Run and Walk

The annual Grey Mountain Summer Solstice Fun Run and Walk hosted by… Continue reading

Letter: We all have a role in fighting climate change

Climate change is arguably the biggest problem facing our world. It is… Continue reading

Letter: Congratulations on the new protected area

Yukon Conservation Society (YCS) wishes to extend its congratulations to all the… Continue reading

Letter: Celebrating Indigenous Peoples Day

Celebrated on June 21, National Indigenous Peoples Day is around the corner.… Continue reading

City news, briefly

A summary of some of the issues discussed at the June 17 Whitehorse city council meeting

Whitehorse training conference highlighted trans health care needs

The conference, hosted by the World Professional Association for Transgender Health, was June 13-15

COMMENTARY: Foreign funding for local environmental groups no conspiracy

Foreign funding doesn’t mean activism isn’t locally grown, says CPAWS Yukon’s executive director

Letter: Yukoners want ‘climate action now’

Yukoners Concerned are excited that despite the basketball game on TV, over… Continue reading

Most Read